Complex work for Wigan crane firm at Manchester brewery

A Wigan crane firm played a key role in a major project at a Manchester brewery.
Watch more of our videos on Shots! 
and live on Freeview channel 276
Visit Shots! now

Ainscough Crane Hire supported Heineken UK in replacing wort kettles using recent additions to its fleet – a pair of LTM 1650-8.1 cranes capable of lifting more than 700 tonnes.

Read More
Candidates announced for Wigan Council local elections 2022

Due to the complexities of the beer production process and the requirement for silos to fill with grain, there was only a window every 21 days to work on the kettle drums.

Hide Ad
Hide Ad
At work at the Heineken UK breweryAt work at the Heineken UK brewery
At work at the Heineken UK brewery

Ainscough was able to complete the job over five days in total, with Heineken remaining operational throughout.

The crane was positioned against a 25m-high building and saw Ainscough lifting at a height of 52m. A 150t crane was used to build up the 650t, which was surrounded by a scaffold walkway to enable access to modify the wort kettles.

Andy Banks, contract lift manager at Ainscough’s Manchester depot, said: “This was a major task to replace tired equipment and ensure the brewery remains efficient. It was only right that our most impressive models were deployed and it’s fair to say that the LTM 1650-8.1 cranes made light work of an intricate job – particularly given the terrible weather.”

The Ainscough team worked on night shifts to accommodate adverse conditions and benefited from wind speed capacity tables incorporated into the model’s design.

Hide Ad
Hide Ad

The LTM 1650-8.1 also incorporates VarioBase, which enables each outrigger to be extended to a different length. The increased safety and ease of use took the strain off the crane driver who could concentrate fully on the hoist.

Around 80m away from the main crane, two 13.5t kettles were built and welded before being lifted from the scaffold to a zebra crossing and finally transferred to the 650t machine, which lifted the kettles into the brewery for use.

Mr Banks added: “This was more than a general maintenance job and required a high level of planning. Leaving a three-week gap between the two replacements ensured that disruption was kept to a minimum and wouldn’t have been possible without these 650t cranes. They afforded significant flexibility and avoided a main road closure.”

Related topics: